Progress invoicing for contractors: how to bill for work completed

Learn how to calculate each progress invoice and the final balance using a €10,000 renovation as an example.

When to use a progress invoice

A progress invoice bills for a portion of a project based on work already completed. It works well for jobs that run for several weeks and have agreed milestones, such as demolition, installation and finishing. A deposit is an advance payment. If you have already invoiced a deposit, account for it according to the terms agreed with your customer.

How to calculate a progress invoice on a €10,000 project

Assume a €10,000 renovation with no deposit or change in scope. At the first milestone the work is 30% complete, so you invoice €3,000. At the second milestone it is 80% complete in total. The work completed is worth €8,000, and €3,000 has already been invoiced, so the second invoice is €5,000. The final invoice is €2,000. Compare amounts on the same basis, either excluding or including tax.

Example project

Renovation €10,000

First progress invoice · 30%
€3,000
Second progress invoice · 50%
€5,000
Final balance · 20%
€2,000

Prepare the invoice and check payment in Faktyline

Use the accepted quote to review the work completed with your customer. Record the progress and the amounts previously invoiced. Prepare the progress invoice in Faktyline, check the project reference, billing period and amount, then track payment in the dashboard. Keep the last progress invoice handy when calculating the final balance.

Faktyline screenshot showing invoiced, paid and unpaid amounts and a revenue chart.
Faktyline dashboard

Turn an accepted quote into an invoice

Compare Faktyline plans